82 percent construction work on Delhi-Mumbai Expressway completed: Nitin Gadkari

File Photo

New Delhi, July 31: As much as 82 per cent of the physical work on the construction of the 1,386 km Delhi-Mumbai Expressway has been completed as a cumulative length of 1,136 km has been built as of June this year, Union Minister for Road Transport and Highways Nitin Gadkari said in a written reply to a question in the Rajya Sabha on Wednesday.

The minister said that the construction of the Delhi-Mumbai Expressway including spurs comprises, “53 Nos. of packages having 1386 km length total 26 Nos. of packages have been completed.”

   

The revised schedule for the completion date of the Expressway is October 2025, he added.

The corridor provides connectivity to major economic centres within Delhi, Uttar Pradesh, Haryana, Rajasthan, Madhya Pradesh, Gujarat and Maharashtra.

As per the detailed project report (DPR), the Expressway will reduce the distance from Delhi to Jawahar Lal Nehru Port (JNPT) in Mumbai by about 180 km and reduce travel time by up to 50 per cent to connected destinations, the minister added.